Project Type |
Liquid Waste |
Project Status |
Construction |
Project Area |
Southern Gulf Islands |
Estimated Cost |
$9,379,909 |
Estimated Start Date |
01-May-2023 |
Estimated End Date |
31-Jan-2025 |
Contracted To / Performed By |
McElhanney Ltd. (Consulting Engineer), Coast Utility Contracting Ltd. |
Description
Background
The Magic Lake Estates (MLE) Sewer Service upgrade works have been underway over the last few years to address the issues facing the aging and failing infrastructure. Condition of the MLE wastewater infrastructure has been documented in past reports and presented at several public open houses held on November 22, 2014, June 6, 2015, February 27, 2016, and April 27, 2019.
Project Funding
Funding for this project is provided by the Green Infrastructure - Investing In Canada Grant Program and Magic Lake Estates Sewer Service.
Project Description
The construction phase of the MLE project will begin in May of 2023. The project includes the decommissioning of the Cannon wastewater treatment plant (WWTP) which will be replaced with a pump station to divert flows for treatment at Schooner WWTP. Schooner WWTP will be upgraded to treat the additional flows from Cannon pump station which includes replacement of other equipment to improve the health, safety, and overall reliability of the facility. At Galleon and Schooner pump stations, the mechanical and electrical components will be replaced, and the remaining pump stations will receive new communication infrastructure.
Future upgrades will focus work at the following facilities:
- Masthead Pump Station
- Cutlass Pump Station
- Buccaneer Pump Station
- Capstan Pump Station
Magic Lake Estates Wetland Restoration Project
As a result of having to remove some wetlands to complete the wastewater treatment plant project, the CRD will be creating a new wetland area in the adjacent Buck Lake vicinity. The wetland restoration work will begin in the Summer of 2024. For more information about this project, please refer to the Magic Lake Estates Wetland Restoration Project located in our additional information section.
Project Schedule:
Next step | Approx. timeline |
Mobilize contractor to site | May 2023 |
Construction period | May 2023 to August 2024 |
Wetland Restoration Project | August to September 2024 |
Test and commission facilities | July to August 2024 |
Warranty review | August 2025 |