Project Type |
Water |
Project Status |
Design |
Project Area |
Central Saanich |
Estimated Cost |
$9,800,000 |
Estimated Start Date |
06-Nov-2023 |
Estimated End Date |
31-Dec-2026 |
Estimated Duration |
3 years |
Contracted To / Performed By |
Jacobs Consultancy Canada (design) |
Description
Work is planned to replace approximately 1.9km of 762mm concrete pipe on Water Supply Main 4, from the Intersection of Central Saanich Road and Mount Newton Cross Road to the crossing of Highway 17.
The CRD secured a $6-million grant through the UBCM Strategic Priorities Fund to assist with this project.