2023-920 Goldstream Water Treatment Plant Chemical Offloading Facilities Upgrade

Dec 22, 2023, 01:00 PM
Project manager:
Contact person:
Shari McCreesh, Purchaser
Project manager phone:
Contact person phone:
(250) 474-9674
Project ID:
2023-920
PublishedDate:
Dec 22, 2023, 01:00 PM
ClosingDate:
Jan 31, 2024, 02:00 PM
Approx. Time Left:
Departments:
Infrastructure Engineering
Project Status:
Concluded
Tender Type:
Invitation to Tender

Awarded to:
G&E Contracting LP

Project Description:

January 16, 2024 - Addendum 1 Posted

January 22, 2024 - Addendum 2 Posted

January 31, 2024 - Unverified Bid Results Posted

_____________________________________________________________________________________________________________________________

CAPITAL REGIONAL DISTRICT

GOLDSTREAM WATER TREATMENT PLANT
CHEMICAL OFFLOADING FACILITIES UPGRADE
CONTRACT 2023-920

INVITATION TO TENDER

 

Sealed Tenders, plainly marked on the envelope "Tender for GWTP CHEMICAL OFFLOADING
FACILITIES UPGRADE CONTRACT NO. 2023-920” will be received by Shari McCreesh, Purchaser,

Integrated Water Services of the Capital Regional District at their offices at 479 Island Highway up to 2:00pm local time on January 31, 2024, at which time they will be opened in private.

The works to be constructed under this Contract generally include, but is not limited to, the following:

The Goldstream Water Treatment Plant (GWTP) requires upgrades to two chemical transfer facilities where

chemical offloading occurs; the sodium hypochlorite and ammonium hydroxide facilities. Specifically, the
outdoor chemical offloading spill containment pads require increased drain and piping sizes, additional
trench drains, and upsized concrete curbs. These upgrades are intended to better prevent spills from being

released into the environment should a spill occur.

Proponents may be awarded follow-on work without a competition.

Digital copies may be downloaded for no cost from www.crd.bc.ca/about/contracts-rfps/ after registering as a vendor and at www.bcbid.gov.bc.ca without registration. Vendors are encouraged to check BC Bid regularly for updates and not rely on e-mail notifications, as e-mail is inherently unreliable and subject to interruptions.

The lowest or any tender will not necessarily be accepted.

A mandatory pre-tender site meeting will be held at the GWTP Head Office, 2995 Sooke Lake Rd., Langford, at 9:00 am, January 9, 2024. After the Safety Orientation and pre-tender meeting, Tenderers will then be taken to the two facility locations to ensure that they have satisfied themselves of everything and of every condition that could affect the execution of the work. Tenderers are encouraged to make enquiries to satisfy themselves of the work requirements.

For information and/or enquiries on this project please contact Shari McCreesh, Purchaser, Integrated Water Services at:

Shari McCreesh, Purchaser
CRD Integrated Water Services
479 Island Highway
Victoria, BC V9B 1H7
Tel: 250.474.9674
Email: PurchasingIWS@crd.bc.ca


Additional Documents:
Additional documents are no longer available for viewing.


(As a Registered Vendor, this will subscribe you to all updates made to CRD Business Opportunities - 2023-920 Goldstream Water Treatment Plant Chemical Offloading Facilities Upgrade)

Send To A Friend

Get Adobe Reader
If you have problems opening an attachment, please ensure that you have your pop-up blocker turned off in both the browser and Google's toolbar if you have it, or set to allow pop-ups from "//www.crd.bc.ca"

Mobile devices are unlikely to open attachments.

If you have difficulty please email the WebDesk quoting the opportunity reference number.