Project Type Water
Project Status Completed
Project Area Metchosin
Estimated Cost $1,000,000
Estimated Start Date 04-Feb-2019
Estimated End Date 31-May-2019
Estimated Duration 4 Months
Contracted To / Performed By CRD Infrastructure Operations

Description

The CRD is replacing approximately 1130m of existing AC watermain with a new 300mm Ductile Iron watermain along Metchosin Road from the Green Acres Golf Course to ~200m east of Brotherstone Road. The existing watermain was installed in 1960 and is nearing the end of its lifecycle.

Whats New

Last updated May 13

  • Updated Project Status

Receive email updates for Metchosin Road Water Main Upgrade

Subscribe

Additional Information

Gary Jay
CRD Integrated Water Services
Infrastructure Operations
250.883.0611